Athletic Facilities Master Plan

  • Prepared site inventory and analysis of existing athletic facilities, including utilization, field layout, soil conditions, circulation patterns and maintenance practices.
  • Facilitated discussions with campus stakeholders (coaches, administration, security, students, etc.) regarding use and expectations.
  • Provided concept scenarios used to determine overall vision and direction of athletic facilities.
  • Prepared phasing options and construction costs for projects.
  • Prepared final written plan with illustrative graphics showing intercollegiate and recreational venues, including a manual of recommended athletic field maintenance practices.

Arts Across The Campus - Outdoor Master Plan

Inventoried current outdoor public art pieces and analyzed future locations on campus and prepared a written report that included:

  • A planning process to evaluate outdoor public art.
  • Guidelines for the selection of outdoor public art.
  • Strategies for the placement of acquired outdoor public art.
  • Other considerations such as temporary art, signage, artist selection, and program opportunities.
  • Illustrative graphic of future outdoor public art locations based on priority, scale and type.

 Parking & Sidewalk Master Plan

Inventoried and analyzed parking, sidewalks and pedestrian corridors, circulation patterns, and conflict areas.  Prepared a written report that included:

  • Inventory and analyze information.
  • Alternatives for new and/or expanded parking.
  • Pedestrian corridor improvements.
  • Design and policy recommendations regarding parking and pedestrian corridors.

Athletic Master Plan: North Campus

  • Prepared schematic site plan illustrating optimum site development for a stadium complex that included a synthetic surface baseball field and softball field.
  • Prime Consultant for the team that included Architects, MEP Engineers, Surveyors, and Site Contractor.  
  • Facilitated timely meetings with campus stakeholders to define program, present multiple concept options, and establish construction costs.
  • Prepared preliminary analysis regarding subsurface soil conditions and storm water management as required by NYSDEC.
  • Prepared SEQRA (State Environmental Quality Review Act) documentation for agency review.
  • Prepared final cost estimate for construction and other project costs.
  • Deliverables included a written report, rendered graphics, and computer generated 3-D animation of the project area.
  • Completed in December 2011.
Campus Master Plan
  • Worked as a sub-consultant to develop a Campus Master Plan.
  • Services included data collection, mapping and estimating.
  • Updated the Campus Master Plan Graphic including design vignettes for proposed campus improvements.
  • Developed estimates for the various campus site improvements identified in the Master Plan totaling over $10 million in the next five years.
  • Master Plan was completed in 2012.