Multi-Phase 2018 Capital Improvement Project
Phase 1
- Removal of existing 6x6 lane track and replacement with new 8x8 lane broken back track at both schools.
- New synthetic turf field within the track at both schools.
- Related athletic stadium improvements at both schools including 1,500-seat bleachers with press box, LED field lighting, scoreboard, field events including steeplechase.
- Storm water management improvements including SPDES Permit.
Phase 2
- Visitor parking to bus loop.
- Replacement of existing roadway and new sidewalk including storm water management to mitigate existing drainage issues.
- Storm water management improvements including SPDES Permit.
- Vehicular and pedestrian circulation, parking, and pavement improvements.
Phase 3
- Tennis court replacement.
- Storm water management including SPDES Permit.
- Concessions plaza.
Phase 4
- Sidewalk and curb replacement.
- NYSDOT coordination for concrete apron replacement.
- Parking lot improvements.
- Storm water management.
- Bus parking and circulation improvements.
- Conversion of existing tennis courts into hardscape play area.
- New one-way road for parent/student drop-off.