2015 Capital Project, completed in 2015

  • $362,000 approximate site construction cost for site improvements at the high school.
  • Reconstruction at front entrance and parking lot reconstruction.

2016 Capital Project, scheduled for completion in 2016

  • $2.7 million estimated site construction cost for site work at multiple school sites.
  • Scope of services at the elementary school includes:  Asphalt patch at storm structure at the bus loop, regrout joints at granite curbs, replace asphalt walk, lawn repair.
  • Scope of services at the middle school includes:  Repair service road and miscellaneous site improvements.
  • Scope of services at the high school includes:  Synthetic turf replacement, athletic track repair including d-areas, asphalt, sidewalk, and curb replacement, baseball field improvements and softball field improvements.