2010 Renovations

  • $2.3 million approximate site construction costs for site work at multiple district properties.
  • Scope of work included pavement and walk replacement.
  • Storm water management including SPDES Permit.
  • Project was completed in 2012.

2015 Capital Improvement Project

  • $5.5 million estimated site construction costs for site improvements at multiple school sites.

Canandaigua Academy

  • Exhibition Field improvements including replacement of the all-weather track and field with perimeter drains, fencing, addition of steeplechase, replacement of the natural grass turf and drainage, replacement of field irrigation.
  • Extension of utilities to lower fields and sanitary system for restroom facility.
  • Reconstruction of six existing tennis courts.
  • Site work related to bleachers, press box, storage, locker room facility.
  • Improvements at the Lower Field include synthetic turf, access road, new 200-space parking area, drainage and walkways.

Canandaigua Middle School

  • Removal of existing tennis courts and replace with eight new courts including nets, paint markings, fencing and color coat.
  • Storm water management.
  • Asphalt walkways, parking lot modifications, portable bleachers and landscaping restoration.